2020 june 29th. The floor elements are laid and topped with with steel reinforcement net. Now it is time to fill up with concrete
2020 june 24th. Today the guys started to crown the outer walls of the first floor in Presika ;-)
2020 june 23rd. The outer walls continue to rise in Presika ;-)
2020 june 19th. The outer walls continue to rise in Presika ;-)
2020 june 19th. Three basement soil-barriers are applied in Presika. 1-Tar mat layer.... 2-Styrofoam 10 cm insulation.... 3-Concrete block initial barrier
2020 june 17th. The outer walls with hollow terracotta blocks are rising;-)
2020 june 10th. The reinforced concrete floor is ready and now they started to rise the outer walls with hollow terracotta blocks ;-)
2020 june 10th. Unloading terracotta wall blocks in Presika ;-)
2020 june 6th. After a couple of days of rain the work is at full speed again. The blocks of the 1st floor are laid and on monday the mould is filled with concrete. Nevio and Lino discuss some details ;-)
2020 june 6th. After a couple of days of rain the work is at full speed again. The blocks of the 1st floor are laid and on monday the mould is filled with concrete ;-)
2020 june 6th. After a couple of days of rain the work is at full speed again. The blocks of the 1st floor are laid and on monday the mould is filled with concrete. Nevio checks that everything is made according to plan ;-)
2020 june 2nd. Today the guys prepare the frame to cast the concrete base carrying the beams of the first floor ;-)